How Long Does a Bathroom Remodel Really Take?
Table of Contents

Understanding realistic bathroom remodel timelines helps you plan around the disruption and set proper expectations for your renovation project.
"How long is this going to take?" It's the first question every homeowner asks, and the answer they get often determines which contractor they hire. Unfortunately, the most accurate answer—"it depends"—isn't very satisfying. And the contractor who says "we'll have it done in a week" is either cutting corners or setting you up for disappointment.
After completing hundreds of bathroom renovations across the Sacramento region—from Roseville and Rocklin to Folsom, Auburn, and Granite Bay—we've developed precise timelines for every type of bathroom project. This guide gives you the real numbers, explains why each phase takes as long as it does, and shows you how to avoid the delays that extend projects beyond their planned schedule.
The Honest Answer
A standard bathroom remodel—where you're gutting the bathroom and installing new tile, vanity, toilet, shower, and fixtures—takes 3-5 weeks of active construction time. Add in the pre-construction phase (design, material selection, ordering, and permitting), and the total timeline from initial consultation to completion is typically 6-10 weeks.
That range reflects the reality that every bathroom is different. A straightforward guest bathroom with standard materials and no surprises behind the walls trends toward the shorter end. A master bathroom with custom tile work, layout changes, and hidden issues discovered during demolition trends longer. The scope of work, material lead times, and your home's specific conditions all affect the final timeline.
Here's the critical point: any contractor who promises a dramatically shorter timeline is either skipping essential steps (like proper waterproofing cure times), using inferior materials, or will extend the project once it starts. Quality bathroom construction requires specific processes that simply cannot be rushed without compromising the result.
Timeline by Remodel Type
| Remodel Type | Construction Time | Total Time (incl. pre-construction) |
|---|---|---|
| Cosmetic refresh | 3–5 days | 1–2 weeks |
| Standard guest bath remodel | 2–3 weeks | 4–6 weeks |
| Standard master bath remodel | 3–4 weeks | 6–8 weeks |
| Tub-to-shower conversion | 2–3 weeks | 5–7 weeks |
| Upscale master bath with layout change | 4–6 weeks | 8–12 weeks |
| Full bathroom addition | 6–10 weeks | 10–16 weeks |
These timelines assume materials are ordered and received before construction begins, permits are in hand, and no major hidden issues are discovered. Each of those variables can add days or weeks if not managed properly.
Day-by-Day Construction Breakdown
Here's what a standard master bathroom remodel looks like on a day-by-day basis. This represents a typical 3.5-week construction schedule:
Days 1-2: Demolition
The existing bathroom is stripped down to bare studs and subfloor. All fixtures, tile, vanity, toilet, and drywall in wet areas are removed. A thorough inspection of the exposed framing, subfloor, and plumbing is conducted. Protection measures (floor runners, dust barriers) are installed throughout the path from the bathroom to the exterior.
Why it takes 2 days: Careful demolition protects the surrounding structure and allows thorough inspection. Rushing demolition risks damaging plumbing lines, electrical wiring, and adjacent finishes.
Days 3-5: Plumbing and Electrical Rough-In
Licensed plumbers relocate or install water supply lines, drain lines, and shower valves according to the new design. Electricians install new circuits, relocate outlets, add recessed lighting rough-in, and wire the exhaust fan. If heated flooring is included, the electrical feed is run to the bathroom.
Why it takes 3 days: Plumbing and electrical work requires precision and code compliance. Multiple trades may need to coordinate access to wall and floor cavities. A county rough-in inspection is scheduled at the end of this phase and must pass before work continues.
Days 6-7: Cement Board and Waterproofing
Cement board is installed on all wall and floor surfaces that will receive tile. The waterproof membrane system is applied to the entire shower area, including all seams, corners, and pipe penetrations. A flood test may be performed on the shower pan to verify waterproof integrity.
Why it takes 2 days: Waterproofing requires proper application and cure time. The membrane needs to dry completely before tile can be applied. Rushing this step leads to the number one cause of bathroom failure—water intrusion.

The tile installation phase takes 5-7 days depending on complexity—it's the longest single phase of a bathroom remodel and cannot be rushed without sacrificing quality.
Days 8-14: Tile Installation
This is the longest single phase and where most of the visual transformation happens. Floor tile is set first, establishing the slope toward drains. Shower wall tile follows, including any niches, accent bands, or pattern work. Wall tile outside the shower is installed next. After tile sets (typically 24 hours), grout is applied and allowed to cure.
Why it takes 5-7 days: Tile installation is precision work. Each tile must be individually cut, leveled, and spaced. Complex patterns, mosaics, and corner details require extra time. Thinset mortar and grout have specific cure times that cannot be accelerated without risking failure. For a standard master bathroom, expect approximately 100-200 square feet of tile across floor and walls.
Days 15-16: Vanity and Countertop
The vanity cabinet is installed, leveled, and secured. If the countertop is stone or quartz, it's templated and installed (or installed from a pre-cut template). Under-mount sinks are positioned and sealed. Plumbing connections are made—supply lines, drain assembly, and P-trap.
Why it takes 2 days: Vanity installation requires precise leveling and wall attachment. Countertop installation with under-mount sinks needs careful alignment and adequate adhesive cure time. Plumbing connections must be tested for leaks before being concealed.
Days 17-18: Fixtures and Trim
The toilet is set with a wax ring and tested. Shower trim (handle, shower head, handheld spray) is installed. Faucets are mounted and connected. The exhaust fan is connected and tested. Light fixtures are installed. All towel bars, robe hooks, and accessories are mounted.
Why it takes 2 days: Each fixture requires individual connection, alignment, and testing. Shower trim must be carefully aligned with tile lines for a professional appearance. Multiple trips to the electrical panel may be needed for final connections.
Day 19: Shower Glass
Frameless or semi-frameless glass panels are installed by a specialized glazier. This is scheduled after all tile and fixtures are in place to ensure precise measurements and fit. The glass is typically templated 1-2 weeks earlier and custom-fabricated for your specific shower dimensions.
Why it takes 1 day: Glass installation is precision work—panels are heavy and must be perfectly plumb and level. Silicone seals need to cure for 24-48 hours before the shower can be used.
Day 20: Paint, Caulk, and Final Details
Final paint touch-ups, color-matched silicone caulking at all tile-to-fixture transitions, mirror installation, grout sealing, and thorough cleaning. The bathroom is inspected using our 50-point quality checklist.
Day 21: Final Walkthrough
You tour the finished bathroom with our project manager, review the completed work, test all fixtures, and note any items for the punch list. Warranty documentation, care instructions, and the final county inspection are coordinated.
The Pre-Construction Phase Most People Forget
The 3-5 week construction timeline is only part of the story. Before any hammer swings, there's a critical pre-construction phase that typically adds 2-4 weeks:
- Design and material selection: 1-2 weeks for design development, 3D renderings, and choosing all materials
- Material ordering and lead times: Stock tiles and vanities are available within days, but specialty tile, custom glass, and certain fixtures can take 2-6 weeks to arrive
- Permit processing: Roseville and Placer County typically process permits within 1-2 weeks for standard bathroom projects
- Scheduling: Good contractors are booked 2-4 weeks out; spring and summer are peak seasons
The takeaway: if you contact a contractor today, your bathroom will realistically be finished in 2-3 months, not 2-3 weeks. Planning ahead and making decisions promptly during the design phase can significantly shorten this timeline.
What Causes Delays
Understanding what causes delays helps you avoid them. Here are the most common delay factors, ranked by frequency:
#1: Material Backorders (Most Common)
The single biggest cause of bathroom remodel delays is materials not being available when construction is ready for them. This is especially common with specialty tiles, custom shower glass, and imported fixtures. The solution: order all materials before demolition begins and verify they're physically in the warehouse or at your home before starting construction.
#2: Hidden Problems During Demolition
Water damage, mold, deteriorated subfloors, and outdated plumbing can add 2-5 days to the project for repair and remediation. While these delays are frustrating, they're necessary—building over problems just creates bigger problems later. A thorough pre-construction assessment can identify some of these issues before demolition, reducing (but not eliminating) the surprise factor.
#3: Homeowner Decision Changes
Changing your tile choice, switching fixture finishes, or modifying the layout during construction can add days or weeks. Each change requires ordering new materials, returning original materials, and potentially redoing work that's already been completed. The best defense: take the time to make thorough, confident decisions during the design phase.
#4: Inspection Scheduling
County building inspections must be completed before certain phases can proceed. Inspection scheduling depends on the county's workload—during busy seasons, you may wait 2-3 days for an inspector. A bathroom contractor with strong relationships with local building departments can often facilitate faster scheduling.
#5: Weather (Seasonal)
While bathroom work is primarily interior, some tasks are weather-dependent. Exterior ventilation ducting can't be installed during heavy rain. Sacramento's summer heat can accelerate thinset dry times (which can be a positive or negative depending on the situation). Winter construction may experience slower material cure times in unheated bathrooms.
How to Keep Your Remodel on Schedule
You have more control over your timeline than you might think. Here are proven strategies for keeping your project on track:
- Order materials early: All materials should be received and inspected before demolition begins. No exceptions.
- Finalize all decisions during design: Choose every tile, fixture, paint color, and hardware finish before construction starts. Put a bookmark on each decision and commit to it.
- Be available for questions: During construction, your contractor will need answers quickly. A 24-hour delay on a decision often creates a 2-3 day construction delay.
- Avoid changes during construction: Every mid-project change creates a cascade effect. What seems like a simple swap often involves reordering, re-scheduling, and potentially redoing completed work.
- Trust the process: Some phases look slow because of cure times (waterproofing, thinset, grout). These aren't wasted days—they're essential for a bathroom that lasts decades.

The end result of a properly scheduled bathroom remodel—every phase completed correctly with adequate cure times produces a bathroom that looks beautiful and lasts for decades.
Living Without Your Bathroom During Construction
For most Sacramento-area homeowners, the temporary inconvenience of losing a bathroom during construction is the most challenging aspect of a remodel. Here's how to prepare:
If You Have Multiple Bathrooms
Designate one bathroom as the "family bathroom" for the construction period. Stock it with everyone's daily essentials before demolition begins. Consider adding a simple over-the-door organizer for toiletries if space is tight. The inconvenience is manageable when you plan ahead.
If You Have Only One Bathroom
Single-bathroom remodels require more creative solutions. Options include asking your contractor about phased construction that maintains partial bathroom access, arranging temporary use of a gym or community center shower, staying with family or friends for portions of the construction period, or renting a portable shower trailer for the construction duration.
Protecting the Rest of Your Home
A good contractor contains construction dust and debris with plastic sheeting and zip walls. Floor protection extends from the bathroom to the nearest exterior door. Daily cleanup at the end of each workday keeps the disruption to the bathroom area only.
Why Rushing Costs More Than Waiting
The pressure to "get it done fast" is understandable—nobody enjoys living in a construction zone. But rushing a bathroom remodel creates problems that cost far more in the long run than the inconvenience of a few extra days:
- Insufficient waterproofing cure time leads to membrane failure and water damage within 1-2 years. Repair cost: $5,000-$15,000.
- Rushed tile installation results in lippage (uneven tile surfaces), hollow spots where thinset didn't bond, and cracked tiles from insufficient support. Repair cost: $2,000-$6,000.
- Skipped inspections mean code violations that surface when you sell or make an insurance claim. Remediation cost: $3,000-$10,000.
- Poorly cured grout crumbles and stains prematurely, requiring full regrout within 2-3 years. Cost: $1,000-$3,000.
A bathroom done right takes 3-5 weeks of construction time. A bathroom done fast often takes 3-5 weeks of construction plus another 3-5 weeks of repairs within a few years. Patience during the initial construction saves you money, time, and frustration in the long run.
Frequently Asked Questions
Get a Realistic Timeline for Your Bathroom Remodel
OakWood Remodel provides detailed, phase-by-phase timelines for every project. We manage material ordering, permit scheduling, and construction coordination so your remodel stays on track from day one.
Get a Free Estimate
Call us at (916) 907-8782 or fill out our contact form.